1. Overview
This lesson emphasizes that safety is the primary priority in electrical work, governed by specific federal laws and standards. Here is a breakdown of the key points:
1. Governing Standards and Laws
- OSHA 1926 & 1910: These are federal laws that set the mandatory standards for electrical safety in the workplace.
- National Electric Code (NEC): Becomes law once adopted by a specific state.
- NFPA 70E: Provides the practical guidelines on how to comply with OSHA’s safety requirements.
2. Personal Protective Equipment (PPE)
Under OSHA Standard 1926.95, workers must use proper PPE to prevent injuries to the face, eyes, and body. Essential gear includes:
- Safety glasses and goggles.
- Insulated gloves and tools.
- Work boots and hard hats.
Note: According to NFPA 70 Article 103, PPE is considered the last line of defense in the hierarchy of risk control. It must always be adjusted to match the specific level of electrical hazard present.
3. Rights and Responsibilities
- Employer Duty: Under the Occupational Safety and Health Act of 1970, employers are legally required to provide a safe workplace and ensure employees wear proper PPE.
- Employee Rights: Workers have a "right to know" about safety guidelines and must be provided with necessary training and education.
2. Understanding the Code
This lesson explains that the key to mastering the NEC is understanding its organizational structure. Following the code correctly is essential for protecting both people and property from electrical accidents.
1. The Hierarchy of the NEC
The NFPA 70 (NEC) is organized into a specific hierarchy to help users find rules efficiently:
- Chapters: There are 9 chapters in total.
- Articles: Chapters are divided into articles based on specific topics.
- Parts: Articles may be further broken down into parts.
- Sections & Subsections: This is where the actual rules are located.
2. The First Four Chapters (General Requirements)
Chapters 1 through 4 are "general chapters" that apply to almost all electrical installations. They cover:
- General requirements for installations.
- Wiring and protection.
- Wiring methods and materials.
- Equipment for general use.
3. Key Tools for Interpretation
To navigate and understand the code correctly, the lesson highlights two critical areas:
- Article 90: Provides the introduction and the core purpose of the NEC.
- Article 100 (Definitions): This is vital for interpreting terminology. It helps electricians distinguish between technical terms and everyday "slang." (e.g., Using the technical term "receptacle outlet" instead of just "outlet").
- The Index: A helpful tool for finding information using keywords.
3. General Installation Process
This lesson outlines the step-by-step workflow of a residential electrical installation, from planning and material takeoff to the physical installation of service equipment and wiring.
1. Planning and Material Preparation
- Responsibility: Electricians plan circuits for small residential projects, while architects handle larger ones.
- Bill of Materials (BOM): Created by performing a "material takeoff" using floor plans, panel schedules, and electrical symbols.
- Compliance: The installation must meet or exceed NEC rules to ensure safety.
2. Service Entrance Types
There are two primary ways to bring power from the utility to the building:
- Overhead Service: Uses SE cable (Service Entrance cable) or conductors in conduit (RMC, IMC, or PVC). Must follow NEC Article 230 for specific height and window clearances.
- Underground Service: Involves digging a trench from a transformer to the house. NEC Table 300.5 dictates burial depth (e.g., 18 inches for direct burial in residential settings).
3. Grounding and Bonding
This is a critical safety step to clear "fault currents" (preventing shocks):
- Main Service Disconnect: The main breaker panel where the power first enters.
- Grounding: Connecting the panel to ground electrodes (rods) in the earth using a grounding electrode conductor.
- Main Bonding Jumper: Installed in the panel to connect non-current-carrying metal parts to the neutral conductor.
4. Rough-In: Boxes and Wiring
- Device Boxes: Installed throughout the structure to hold switches, receptacles, and lights based on the blueprint locations.
- Conduit and Cable: * Conduit is measured, bent, and installed to create a path.
- Wires are "pulled" through the conduit or run as cables back to the main service panel.
- Note: While the NEC dictates the size and type of wire, Article 210.52 (referenced as 210.12 in transcript) provides guidelines on the spacing and placement of receptacles.
Key NEC References Mentioned
| Reference | Topic |
| Article 230 | Service entrance clearances and heights. |
| Table 300.5 | Minimum burial depths for underground wiring. |
| Article 338.2 | Definition and use of Service-Entrance Cable (SE). |
| Article 210 | Branch circuit requirements and outlet locations. |
4. Wooden Structure
This lesson covers the specific regulations and environmental factors involved when installing electrical systems in wood-frame structures.
1. Building Classification
- IBC Type 5: According to the International Building Code (IBC), wooden premises (such as single and two-family dwellings) are classified as Type 5 construction.
- Installation Timing: Electrical work begins only after the roof is installed. This protects the components from environmental damage (rain, snow, etc.).
2. Environmental Considerations
- Dry Locations: Once the building is "dried-in" (roof on), the interior is classified as a dry location.
- Wiring Method (NM Cable): Because it is a dry location and Type 5 construction, Type NM (Non-Metallic sheathed cable) is the standard wiring method.
- Protection: Cables and raceways are selected specifically to provide mechanical protection for the conductor's insulation.
3. Compliance and Safety
- Blueprints: Electrical engineers specify the exact wiring methods on the blueprints, which contractors use to provide cost bids.
- Listing and Labeling: Per NEC Article 110.3(B), all installed equipment must be "listed and labeled" (e.g., by UL or Intertek) and used according to its instructions.
- Testing: During installation, electricians must ensure circuits are free from short circuits and ground faults to prevent fires or equipment damage.
Key Technical Standards
| Standard | Purpose |
| IBC Type 5 | Classification for wooden frame residential buildings. |
| Type NM Cable | Most common wiring method for residential "dry" wood framing. |
| NEC 110.3(B) | Requires equipment to be used according to its listing and labeling. |
5. Metal Framing in Type 1 & 2 Steels & Conctrete Structures
This lesson focuses on the construction types and specific wiring methods required for high-rise, commercial, and multi-family buildings made of non-combustible materials.
1. Building Classifications
- Type 1: High-rise residential and commercial buildings. Constructed entirely of non-combustible materials, including the roof.
- Type 2: Often used for condominiums. Similar to Type 1, but the roof material may be combustible.
- Significance: The building type dictates the allowed wiring methods and environmental conditions for use.
2. Metal Framing (MC Cable)
In steel-framed buildings, Metal Clad (MC) Cable is the standard wiring method (per NEC Article 330).
- Flexibility: Components can be installed while the frame is being built or after it is finished.
- Support & Securing: * Per Article 330.30, MC cable must be supported every 6 feet.
- This requires fewer support points than other methods, making it highly efficient.
- Installation uses self-tapping screws and specific fasteners to secure cables to the metal studs.
3. Concrete Structures (PVC and EMT)
The wiring method changes based on whether the electrical components are inside or outside the concrete.
- During the Pour (In-Slab): PVC conduit is typically used inside the concrete slab.
- On the Wall (Exposed): Once the wiring exits the concrete, it transitions to EMT (Electrical Metallic Tubing).
- Securing to Concrete: Per Article 358.30, EMT must be secured using specialized fasteners like sleeve anchors, which require pre-drilling into the concrete surface.
Key NEC References & Comparisons
| Feature | Metal Framing (MC) | Concrete/Exposed (EMT) |
| NEC Article | Article 330 | Article 358 |
| Max Support Gap | 6 Feet | Varies (Typically 10ft, but closer at boxes) |
| Common Fastener | Self-tapping screws | Sleeve anchors |
| Primary Use | Inside metal stud walls | Exposed on walls or transitioning from slabs |
'HVAC Fundamental (English) > Fundamental Full' 카테고리의 다른 글
| Introduction to Fire Alarm Systems (0) | 2026.01.05 |
|---|---|
| Reading Schematics and Drawings (Full ver.) (0) | 2026.01.03 |
| Introduction to Refrigeration Systems (Full Ver.) (0) | 2026.01.02 |
| Temperature, Pressure, and Heat (Full ver.) (1) | 2025.12.29 |
| Residential HVAC Controls (Full ver.) (0) | 2025.12.27 |